Key facts
- Who it is for
- Developers and investors building for sale or lease
- Drawdowns
- Usually monthly, against QS certified work
- Core lender test
- Undrawn facility must cover cost to complete
- Preferred contract
- Fixed price with a licensed builder
- Interest
- Usually capitalised during the build
- Overruns
- Funded by the borrower before further drawdowns
What is construction finance?
Construction finance is the part of a development finance facility that pays for the build, released in stages as work is completed and certified. This page covers commercial and development construction funding: townhouses, apartments, subdivisions, and commercial or industrial buildings built for sale or investment.
Construction finance is not the same as a home construction loan. A home construction loan is a residential mortgage for an individual building a house to live in, usually paid in a handful of fixed stages (slab, frame, lock-up, fit-out, completion), checked by the bank's valuer and generally regulated under consumer credit law. An owner-builder loan is a variation for people managing their own home build.
Construction finance for a development is a business purpose facility, normally to a company or trust. It is drawn monthly against a quantity surveyor's report, interest is usually capitalised, and repayment comes from sales or refinance of the finished project. ASIC's guidance is that loans to companies are not subject to the national consumer credit legislation, so consumer protections such as responsible lending generally do not apply.
How do progress claims and the drawdown schedule work?
Progress claims are the builder's periodic invoices for work completed, and the drawdown schedule is the lender's forecast of when those claims will be paid from the construction finance facility. Most commercial building contracts provide for monthly claims based on the value of work done, not fixed stages.
- The builder submits a progress claim to you or your superintendent, itemised against the contract trades.
- The lender's quantity surveyor inspects the site and assesses the claim.
- The quantity surveyor issues a report certifying the value of work in place and the cost to complete.
- You sign a drawdown request, and the lender checks its conditions, such as insurance currency and evidence that subcontractors have been paid.
- The lender pays the certified amount, normally direct to the builder, and adds it to your loan balance.
Your equity goes in first. Lenders almost always require your contribution to be fully spent on land and early costs before the first construction drawdown. The share of cost a lender will fund is explained in the guide to presales, LVR and loan to cost.
What does the quantity surveyor report and what is the cost to complete test?
The quantity surveyor (QS) reports to the lender on whether the budget is adequate and how much work has been done, and the cost to complete test checks that the money left in the facility is enough to finish the project. The QS is engaged by the lender and paid for by you.
Before approval, an initial QS report reviews the building contract, plans, approvals, program and budget, and says whether the contract sum and contingency are realistic. During the build, a progress report with each claim covers:
- the value of work completed to date and the amount recommended for payment
- approved and pending variations
- progress against the construction program and the forecast completion date
- the cost to complete, including consultants and statutory charges still to be paid
The cost to complete test is simple: the undrawn facility, plus any equity still to be contributed, must be at least equal to the QS's cost to complete. If a claim would leave the project short, the lender will not pay it in full until you inject the difference. This test is the lender's main control, because a half-built project is worth far less than the money spent on it.
How do contingency and retention protect the project?
Contingency and retention are two separate buffers in construction finance: contingency is an allowance in your budget for unknown costs, and retention is money held back from the builder until the work is finished properly.
Contingency. Lenders expect a contingency line in the feasibility, commonly around 5 to 10 per cent of construction cost as a general guide, with more for difficult sites, refurbishments or early-stage documentation. It is released only when the QS confirms a legitimate cost that is outside the contract.
Retention. Most building contracts let you withhold a small percentage of each progress claim, or hold bank guarantees instead, up to a cap set in the contract. Part is typically released at practical completion and the rest at the end of the defects liability period. Retention gives you leverage to have defects fixed and some cover if the builder fails late in the job.
Should the building contract be fixed price or cost plus?
A fixed price building contract is what most construction finance lenders require, because it sets the contract sum up front and leaves the builder carrying most of the risk of price rises. A cost plus contract passes actual costs through to you with a margin on top, so the final cost is unknown when the loan is approved.
| Feature | Fixed price (lump sum) | Cost plus |
|---|---|---|
| Price certainty | Contract sum agreed before work starts | Final cost known only at completion |
| Who carries cost increases | Mostly the builder, apart from variations and allowances | You |
| Lender appetite | Accepted by most lenders | Limited, mainly non-bank and private lenders |
| Usual lender response | Standard contingency | More equity, a larger contingency and closer QS review |
A fixed price is only as fixed as its exclusions. Provisional sums, prime cost items and rise and fall clauses all let the price move, so the QS will look for them. Owner-builder structures, where you manage the trades yourself, are funded by a narrower group of lenders and usually at lower leverage.
What happens if construction costs run over budget?
If construction costs run over budget, you are expected to fund the overrun before the lender releases further construction finance. The sequence is usually predictable.
- Contingency is used first. The QS reallocates the allowance to the approved variation or cost increase.
- You are asked for more equity. Once contingency is gone, the cost to complete test fails and the shortfall must be paid in cash.
- The lender may consider an increase. This needs fresh credit approval, depends on the loan to cost and end value limits still being met, and is not something to rely on.
- Subordinated funding may fill the gap. Mezzanine finance or new equity partners can be brought in with the senior lender's consent, at a high price.
- Drawdowns stop. An unfunded shortfall is normally an event of default. Lenders hold a side deed with the builder that lets them step in and finish the project.
Delays cost money as well. A longer program burns through the capitalised interest allowance and can run the facility past its expiry date. Ask for a term with a realistic buffer after practical completion for titles, settlements or a residual stock loan.
Who provides construction finance and how do you apply?
Construction finance is provided by banks, non-bank lenders and private lenders, and each sets different rules on presales, leverage and builder strength. Banks tend to be cheapest and most conservative, and APRA's credit risk guidance for banks lists speculative development among the higher-risk loan types that may warrant portfolio limits. Non-bank and private lenders fund projects with fewer presales or less developer experience, for a higher margin.
A lender will want the development approval, stamped plans, the signed building contract, builder financials and insurance, a full feasibility, and details of your equity and experience. If you intend to keep the finished building, ask early how the facility converts or refinances to a commercial property loan on completion.
Because policy varies so much, a commercial finance broker can compare lenders against your contract type and program. To have a broker partner look at your project, send the details through the enquiry form. This site is not a lender and cannot promise an approval or a timeframe.
Frequently asked questions
Is a construction loan the same as construction finance?
The terms overlap, but they usually describe different products. A construction loan from a bank's home lending arm is a residential mortgage for building your own house, paid in fixed stages. Construction finance in a commercial sense funds a development or commercial building for a business purpose, with monthly drawdowns certified by a quantity surveyor and repayment from sales or refinance.
How often can you draw down on construction finance?
Most facilities allow one drawdown a month, timed to the builder's progress claim under the contract. Each drawdown needs a quantity surveyor's report, a signed drawdown request and confirmation that the lender's conditions are still met. Allow time between the claim date and payment, because the builder's contract will set a deadline for you to pay.
Who pays for the quantity surveyor on a construction loan?
The borrower pays, although the quantity surveyor is appointed by and reports to the lender. You are charged for the initial report before approval and for an inspection and report with each progress claim. These fees should be included in your feasibility as a finance cost, along with valuation and legal fees.
Can you get construction finance as an owner-builder?
Some lenders will consider it, but the choice is narrow. Most construction finance lenders want a fixed price contract with a licensed, independent builder. Where the developer and builder are related, or you are managing trades yourself, expect lower leverage, a larger contingency and closer quantity surveyor scrutiny, mostly from non-bank or private lenders.
Does the lender pay the builder directly?
Usually, yes. Once the quantity surveyor certifies a progress claim and you sign the drawdown request, most lenders pay the certified amount straight to the builder and pay consultants or authorities on invoice. Paying direct helps the lender confirm that loan funds are going into the project and that the cost to complete figure stays accurate.
What is practical completion in construction finance?
Practical completion is the point defined in the building contract when the works are finished apart from minor defects and the building can be used for its purpose. It usually triggers the final progress claim, release of part of the retention and the start of the defects liability period. For the lender it marks the move from construction risk to sales or refinance.
Sources
Written by
Development and private lending writer
Thandiwe covers development finance and the private lending market. She writes about how facilities are sized and drawn, what an exit strategy has to prove, and the warning signs in short-term loan offers, with the aim that readers understand the cost of a deal before they sign it.
Last reviewed 24 November 2026. See how we research and check our guides on the editorial team page.
This page is general information, not credit, tax or financial advice. Figures describe typical market practice and are not quotes. See our disclaimer.